Worship Center We are obtaining quotes on new lighting and tracks in the Worship Center so that when Epiphany re-orients the altar and chairs, the lighting will not need to be disengaged and physically moved by a volunteer.
Community Center The Community Center work is completed. We will evaluate renovations for the Library and Nursery in the near future.
Epiphany House
The remaining windows have recently been replaced. The exterior doors, and french doors in the living and dining rooms, as well the Pastor and Business Manager offices, will be replaced soon.
Our next phase is renovating the kitchen and evaluating the bathrooms for renewal. Painting and flooring will then be addressed.
Geothermal installation is expected in early March.
Many volunteers have assisted in organizing these new spaces, and we are very grateful for all the continued work they do for us!