Restrooms are open and ready to use. We appreciate your patience during this process.
The Serving Kitchen renovation is complete. Next, we will organize the new cabinetry and finalize the instructions for the new coffee machine! On Epiphany weekend, it kept up with all the guests providing (we hope) delicious coffee fast!
Rectory:
Roughed-in electrical work is complete, along with most of the major plumbing. We are grateful to our electrician, Payne Electric, for donating several beautiful light fixtures.
Kitchen and bathroom cabinetry has been ordered, along with kitchen appliances. We hope to see them installed in late January or early February.
The construction of the bathroom walls and doors is finished. Only the tile still needs to be installed.
Along with directing and managing our subcontractors, Tom Frank is painting all the walls, trim, and doors.
Hardwood flooring is being installed this week and will be sanded and finished soon.
We have started looking at furniture to furnish the house and prepare for our Pastor.
A group of volunteers is handling the supplies needed to start up a household - linens, utensils, light fixtures, etc.
We continue to be mindful of our expenses for all the renovations. Amazingly, we can fund our work with the donations received for the Capital Campaign. If you are new to the parish and interested in learning
more about the campaign and our renovations, please read the Celebrating Our Future Capital Campaign webpage.